Expansion phases

  • Late 2012: Begin east side right-of-way clearing and Redstone Arsenal fence relocation
  • Early 2013: Begin utility relocation
  • Late 2013: Begin construction on northbound lanes, east side of Zierdt, upon completion of utility relocation
  • Late 2014: Begin construction on southbound lanes, west side of Zierdt, upon completion of northbound lanes and right-of-way acquisition
  • 2015: Project completion