Huntsville road work scheduled for 2010 - WAFF-TV: News, Weather and Sports for Huntsville, AL

Huntsville road work scheduled for 2010

STREET RESURFACING PLANNED FOR FY 2010 (ALL DATES ARE WEATHER DEPENDENT)

STREET

FROM

TO

DATE SCHEDULED

CONCRETE WORK ON THE FOLLOWING:

     

RIVLIN RD

BARCODY RD

DEAD END

12/28/09-12/31/09

OWENS DR

HERMITAGE AVE

DEAD END

12/28/09-12/31/09

LOCUST ST

CALIFORNIA ST

OWENS DR

12/28/09-12/31/09

KENT RD

OVERTON RD

WHITESBURG DR

 
       

MILLING &PAVING THE FOLLOWING:

     

PRINCESS ST

MASTIN LAKE RD

FORSYTHE DR

12/28/09-12/31/09

DAWNWOOD DR

MASTIN LAKE RD

DOAK DR

12/28/09-12/31/09

RIVLIN RD

BARCODY RD

DEAD END

12/28/09-12/31/09

Powered by Frankly